Work that is a building operation requires a Building Permit.
It is an offence under the Building Act 1988 to perform any of the works listed below unless a permit has been obtained in writing from the Building Official.
Residential Buildings
the excavation or quarrying of any land, including that under an existing building;
the demolition of any building or structure except where the following conditions are met:
the building or structure is located a minimum of 25 feet from any road or boundary; and
the building does not contain any old vinyl floor tiles (exceeding 30 years old) or any pipe insulation (exceeding 30 years old) or asbestos corrugated roofing; and the Department of Health has conducted a preliminary inspection to confirm the above.
the erection of any building or structure, whether permanent or temporary;
the carrying out of any structural alteration or extension of any building, including the removal of any parts of internal load bearing walls or of fire partitions or walls;
the carrying out of works for the purpose of effecting a material change in use of the building or premises;
the installation or renewal of an electrical system;
the installation or renewal of any plumbing or drainage or sewage disposal system;
the installation or renewal of any gas fuel system;
the reconstruction of a building;
the conversion of a movable object into a building;
the removal of a building from one site and its re‐erection elsewhere;
the roofing over of an open space between walls or buildings;
the installation, renewal, renovation or change of any mechanical system containing more than 6.6 lbs (3kg) of refrigerant; and,
the installation of any fuel burning system other than a cook top or oven even if the fuel burning system piping is not being altered.
Commerical Buildings
the excavation or quarrying of any land, including that under an existing building;
the demolition of any building or structure that is within 25 feet of a road or to which the public has access;
the erection of any building or structure, whether permanent or temporary;
the carrying out of any structural alteration or extension of any building, including the removal of any parts of internal load bearing walls or of fire partitions or walls;
the carrying out of works for the purpose of effecting a material change in use of the building or premises. A material change in use shall mean a change from one use group to another in accordance with the building codes;
the installation or renewal of an electrical system;
the installation or renewal of any plumbing or drainage or sewage disposal system;
the installation or renewal of any gas fuel system;
the installation or renewal of any mechanical systems;
the installation, renewal, renovation or change to any mechanical system containing more than 6.6 pounds (3 kg) of refrigerant;
the reconstruction of a building;
the conversion of a movable object into a building;
the removal of a building from one site and its re-erection elsewhere; and,
the roofing over of an open space between walls or buildings.
Letters of objection and/or representation should be emailed to planningfrontdesk@gov.bm referencing the PLAN or SUB number in the subject line.
Seven Arches Building, 3rd Floor, 44 Church Street, City of Hamilton, HM12, Bermuda
Subscribe to our mailing list to receive an email notification whenever new Planning Applications have been advertised in the Official Gazette.